WORK ON LANCASTER BUILDING SITE CONTINUES

Posted in Uncategorized | Comments Off on WORK ON LANCASTER BUILDING SITE CONTINUES

PROGRESS THROUGH JULY 14 ON THE 2012 LANCASTER BUILD

Posted in Uncategorized | Comments Off on PROGRESS THROUGH JULY 14 ON THE 2012 LANCASTER BUILD

Progress Through July 4.

Posted in Uncategorized | Comments Off on Progress Through July 4.

Week of June 18, 2012

The footings and foundation have been poured and all forms are off.  The center support beam is in place.  The sill plates have been cut and drilled.  We will put in the floor joists and floor sheathing and get to the framing as soon as is possible.

Posted in Uncategorized | Comments Off on Week of June 18, 2012

Week of June 11, 2012

The 2012 Partner Family has been chosen.

Construction has begun on the new home on Mechanic Street in Lancaster.  The foundation hole is in.

Anyone interested in volunteering or donating goods should contact Habitat for Humanity Ammonoosuc  Region (HFHAR) at 603-616-2515 or email ammonoosuchabitat@gmail.com.

HFHAR will have information booths every other week on Saturdays, starting on June 9th, at the Lancaster Farmer’s Market on Sundays, starting on June 17th at the Littleton Farmer’s Market.   Stop by and talk to us.

Posted in Uncategorized | Comments Off on Week of June 11, 2012

2012 Build – Lancaster

HFHAR has purchased a property on Mechanic Street in Lancaster and is gearing up to build in 2012.

If you would like to volunteer time or make a donation please contact us!

Habitat for Humanity Ammonoosuc Region, P.O. Box 46, Littleton, NH 03561.

Our email address is: ammonoosuchabitat@gmail.com

And our phone number is: 603-616-2515

Posted in Uncategorized | Comments Off on 2012 Build – Lancaster

2011 Build Photos

Posted in Uncategorized | Comments Off on 2011 Build Photos

2011 Build

Construction continues at the build site on Thorn Hill road in Bethlehem with the partner family.

This past week we had 12 volunteers on Thursday and 11 volunteers on Saturday.  We are making good progress.  So far we are about 3 weeks ahead of last year’s building schedule.

This week,  with the emphasis on truss installation,  we could again use about 10-12 volunteers for each work day.  Starr Construction will have people helping us with the trusses. We hope to keep things moving towards a mid-November finish.

Posted in Uncategorized | Comments Off on 2011 Build

2011 Build Photos

Photos from the 2011 build at Thorn Hill in Bethlehem.

Posted in Uncategorized | Comments Off on 2011 Build Photos

2011 – Moving Forward!

We have a Purchase and Sales Agreement on land in Bethlehem and the Family Selection process is underway. We should be building this summer, so stay tuned for updates!

Posted in Uncategorized | Comments Off on 2011 – Moving Forward!